1. Background

Following the fires at Grenfell Tower in London and at the Lacrosse Building in Melbourne, the Victorian Government has sought to develop policy solutions to rectify the dangerous combustible cladding that has been installed at many multi-storey residential and commercial buildings in Victoria.

This concern about dangerous combustible cladding has now sparked legislative change. In September 2020, the Victorian Parliament passed the Cladding Safety Victoria Bill 2020 (Bill), which is expected to be made into law shortly.

2. What does the Bill do?

Establishment of Cladding Safety Victoria

The Bill establishes Cladding Safety Victoria (CSV) as a separate body corporate, so that it will no longer operate as a business unit of the Victorian Building Authority. It prescribes the way in which CSV will carry out cladding rectification in Victoria, allowing municipal building surveyors to notify CSV of buildings that they suspect to have defective cladding, as well as allowing CSV the ability to determine if it will grant financial assistance for cladding rectification work.

Rectification of cladding

Where CSV agrees to provide financial assistance, it will enter into a funding agreement with the affected building owner or owners corporation to enable rectification of that cladding. Entry into the program is voluntary, but it will undoubtedly be very attractive to building owners seeking funding to replace dangerous cladding at their building.

To facilitate and oversee the rectification works, CSV appoints an Independent Project Manager whose role includes appointing the builder and architect, determining the scope of works and superintending the project once construction begins.

Extended limitation period for cladding building actions

The Bill also extends the limitation period for a “cladding building action” from 10 years to 12 years. This is defined to mean as “a building action in connection with, or otherwise related to, a product or material that is, or could be, a non-compliant or non-conforming external wall cladding product”.  The extension of the limitation period allows owners of buildings affected by combustible cladding to bring a claim up to 12 years after their date of issue of an occupancy permit.  This will only apply to building owners and owners corporations whose claddings building actions were time barred between 16 July 2019 and 12 months after the Bill becomes law.

This measure also supports CSV’s ability to recoup some of the funding it provides to building owners. Under the Building Amendment (Cladding Rectification) Act 2019, CSV has a subrogation right which allows it to step into the shoes of the building owner in order to bring legal proceedings against third parties responsible for the non-compliant cladding being installed. 

3. How we can help

This Bill marks a further step in this developing area of law. We have assisted owners corporations and builders commence or defend building actions in relation to combustible wall cladding, and we have advised owners in receipt of financial assistance from CSV.

We are able to help Victorian owners and owners corporations navigate their rights and responsibilities under these changes, and carefully consider whether they now have an entitlement to commence a building action for combustible wall cladding. We are also able to help builders determine whether they are potentially liable for the extended limitation periods.

 

Key contacts

Share on LinkedIn Share on Facebook Share on Twitter
    You might also be interested in

    The Victorian Government has now imposed an industry-wide shutdown of the sector.

    22 September 2021

    On 16 September 2021, the Victorian Government announced a number of changes to the COVID-related restrictions that apply to individuals and businesses in the state.

    20 September 2021

    The High Court’s recent decision in Price v Spoor [2021] HCA 20 has confirmed that parties can effectively contract out of limitation periods imposed by statute. The decision provides certainty as to...

    08 September 2021

    As foreshadowed in our previous update on building reforms in NSW, various reforms under the Design and Building Practitioners Act 2020 (NSW) (the Act) came into effect on 1 July 2021.

    26 July 2021

    You may also be interested in...

    This site uses cookies to enhance your experience and to help us improve the site. Please see our Privacy Policy for further information. If you continue without changing your settings, we will assume that you are happy to receive these cookies. You can change your cookie settings at any time.

    For more information on which cookies we use then please refer to our Cookie Policy.